Work has begun on the £33m Bury Market regeneration project ensuring the market can continue to thrive for many years to come!
New canopies are currently being installed to create a more attractive and visible outdoor market and foundation works for the Flexi Hall are in progress, ready for the construction starting in the summer.
Let's support the traders!
Bury Market will be open for business throughout the regeneration project, including during the construction phase of the Flexi Hall and while enhancement works are carried out to the outdoor market.
Site works progress video
Watch the latest video showcasing the exciting progress of the £33 million #BuryMarketRegen project and take in a bird’s eye view of the transformation.
Site works update - August/September 2025
Flexi hall
- Finish installing pile caps (thick concrete mats that rest on top of the deep columns that were installed into the ground)
- Build the steel frame for the first floor
- Place the concrete for the upper floors
- Build the timber frame
- Prepare the ground to install floor slabs and ground beams, to provide a stable base for the external and internal walls
- Install fire protection to steel frame
- Continue installing drainage
Canopies
Canopy 1
- Finish works on the mechanical and electrical systems including, lighting, fire alarm system, installing distribution boards, fitting low level steels to the canopies and decoration to the canopy soffits
- Install upright cladding, to help insulate the canopy and make it weather resistant
Canopy 2
- Finish works on the mechanical and electrical systems including, lighting, fire alarm system and decoration to the canopy soffits
- Install upright cladding, to help insulate the canopy and make it weather resistant
- Install fascia boards and soffit flashings, to help make the canopy weather resistant
Site works - stages
- April 2025: Continue installing market canopies
- July 2025: Start Bury Market Flexi Hall construction
- March 2026: Start landscaping improvements
- July to August 2026: Scheme completion
Site visits and works in pictures
Construction site
Site works
Flexi Hall ground breaking event video
Hear from the Leader of Bury Council, Councillor Eamonn O'Brien, as he talks about the £33m scheme designed to enhance Bury Market and the town centre offer.